Section 57 of the Income-tax Act, 2025: Revenue recognition for construction and service contracts
This section mandates the specific accounting methods—percentage of completion, project completion, or straight line—for determining profits and gains from construction and service contracts, along with rules for including retention money and excluding incidental income from contract costs.
Last updated
Text of the section
57. Revenue recognition for construction and service contracts.
(1) The profits and gains arising from a construction contract or a contract for providing services, shall be determined on the basis of percentage of completion method, subject to provisions of sub-section (2), as per the income computation and disclosure standards notified under section 276(2).
(2) For the purposes of sub-section (1), the profits and gains arising from a contract for providing services shall be determined—
(a) on the basis of project completion method, if the duration of such contract is not more than ninety days;
(b) on the basis of straight line method, if the contract involves indeterminate number of acts over a specified period of time.
(3) For the purposes of percentage of completion method, project completion method or straight line method under this section,—
(a) the contract revenue shall include retention money;
(b) the contract costs shall not be reduced by any incidental income in the nature of interest, dividends or capital gains. [ Similar to Section 43CB from The Income Tax Act, 1961. - Also Refer ]
What it means for CAs
- Profits and gains from construction contracts or service provision must generally be determined using the percentage of completion method, in accordance with income computation and disclosure standards notified under section 276(2).
- Service contracts with a duration of ninety days or less require profit determination using the project completion method instead of the percentage of completion method.
- Service contracts involving an indeterminate number of acts over a specified period of time require profit determination using the straight line method.
- Contract revenue computed under these methods must include retention money.
- Contract costs must not be reduced by any incidental income in the nature of interest, dividends, or capital gains.
When you’ll meet it
- Reviewing the computation of taxable profits for a client engaged in long-term construction projects or service contracts to ensure the percentage of completion method is applied correctly.
- Auditing short-term service contracts lasting ninety days or less where the client has applied the project completion method for income determination.
- Examining service contracts that involve an indeterminate number of acts over a specified period to verify the application of the straight line method.
- Verifying whether a client's computation of contract revenue properly includes retention money.
- Checking if a client has improperly reduced contract costs using incidental income such as interest, dividends, or capital gains.
Points to check
- Verify whether the contract is for construction or services to determine the applicable calculation method.
- Check the exact duration of service contracts to confirm if they exceed ninety days for the purpose of applying the project completion method.
- Ascertain if service contracts involve an indeterminate number of acts over a specified period, triggering the straight line method.
- Ensure that contract revenue calculations explicitly include any retention money.
- Confirm that contract costs have not been reduced by incidental income like interest, dividends, or capital gains.
FAQs
Which method must be used to determine profits and gains from a construction contract?
Profits and gains from a construction contract must be determined on the basis of the percentage of completion method, subject to the income computation and disclosure standards notified under section 276(2).
When can a service contract use the project completion method?
A service contract can use the project completion method if the duration of the contract is not more than ninety days.
How should contract costs be treated regarding incidental income?
Contract costs must not be reduced by any incidental income in the nature of interest, dividends, or capital gains.
CBDT concordance
The CBDT’s own sub-clause-level mapping between the Income-tax Act, 1961 and the Income-tax Act, 2025 for this section.
| 1961 provision | 2025 provision |
|---|---|
43CB Computation of income from construction and service contracts | 57 Revenue recognition for construction and service contracts |
Source: CBDT concordance table
All sections of Income-tax Act, 2025
This page explains the section in plain language for chartered accountants and is not legal advice.